Project Description
Client: 3 Ways Ltd
Project: Drive Screen Fence in place of railing system
Location: Clapham Junction Approach, Wandsworth, London SW11 2QP (Night Work)
Duration: Start date: 18/10/2020 Three Phase installation – Completion date: 21/10/2021
Description of works: Driver Screen Fence in place of railing system.
We have been working closely with this client for a number of years with some challenging installation which we have achieved.
Products installed
60mm x 60mm x 3mm x 2.0m long SHS section.
3000mm width x 2030mm high panels 2No. 8mm horizontal wires surrounding a 6mm vertical wire set. in a 200mm x 50mm mesh aperture.
PVC weave comprising of 650g/m2.
Zinc spray.
M8 nuts bolts washer.
For our installation teams it was a pleasure to work on a clear site with a very helpful client’s agent and site manager.